The essential toolkit for Prince2™ & Microsoft Project



p2msp voor Nederland!
Click here to visit our Dutch partner site

New to Prince2™?
click here to learn more about this hugely popular PM methodology

New to MS Project?
click here to learn more about the world's #1 project scheduling software

Coming soon
p2msp 2009!

click here to see some preview videos of the new 2009 version

Back to Sample Outputs

Monthly Highlight Report

Below is an example of a more complex monthly highlight report produced by p2msp, showing the data automatically populated by p2msp.

 

 

 

 

HIGHLIGHT  REPORT

 

Project Name

p2msp Sample Project.mpp

 

 

Release:

Final

Date:

4th April 2006

 

 

 

 

Author:

Susan Smith

Company:

XYZ Corporation

 

 

 

 

Period From:

01/03/2006

 

 

Period To:

31/03/2006

 

 

 

 

 

 

Project Subject:

Revised Corporate Strategy

 

 

 

 

Project Category:

 

 

 

 

 

Project Comments:

Project Actuals updated to 31/03/2006

 

 

 

 


 

Document History

 

 

Document:

This document is only valid on the day it was printed.

 

Location:

 

 

 

Revision History

 

 

 

 

Revision Date

Previous Revision Date

Summary of Changes

Changes Marked

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Distribution

This document has been distributed to:

 

 

 

 

Name

Title

Date of Issue

Version

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

Highlight Report

Purpose of Document

To provide the Project Board with a summary of the stage status at intervals defined by them.

Project status summary

 

Dates.

Start:

Mon 16/01/06

Finish:

Tue 08/08/06

Baseline Start:

Mon 16/01/06

Baseline Finish:

Thu 06/07/06

Actual Start:

Mon 16/01/06

Actual Finish:

NA

Start Variance:

0 days

Finish Variance:

23 days

 

Duration.

Scheduled:

147 days?

Remaining:

94.83 days?

Baseline:

124 days?

Actual:

52.17 days

Variance:

23 days?

Percent Complete:

35%

 

Work.

Scheduled:

4,048 hrs

Remaining:

2,520 hrs

Baseline:

3,664 hrs

Actual:

1,528 hrs

Variance:

384 hrs

Percent Complete:

35%

 

Costs.

Scheduled:

242,950.00

Remaining:

141,270.00

Baseline:

242,700.00

Actual:

101,680.00

Variance:

250.00

 

 

 

Earned Value.

Planned Value:

104,458.06

Schedule Variance:

-16,798.36

Earned Value:

87,659.71

Schedule Variance %:

-16%

Actual Cost:

101,026.27

Schedule Performance Index

0.84

Budget at Completion:

242,700.00

Cost Variance:

-13,366.56

Estimate at Completion:

279,707.48

Cost Variance %:

-15%

Variance at Completion:

-37,007.48

Cost Performance Index:

0.87

To Complete Performance Index:

1.09

 


 

Delivery Progress This Period.

Products Started.

ID

Name

Purpose

Start Date

End Date

% Complete

 None

 

 

 

 

 

 

 

 

 

 

 

 

 

Products In-Progress.

ID

Name

Purpose

Start Date

End Date

% Complete

 3.1

Environment Analysis

  1. To establish a view of the important external (and possibly internal) developments taking place around the organisation, including an understanding of why these are strategically significant.
  2. To develop an understanding of market opportunities which can be built on and threats which must be overcome or circumvented.
  3. To provide, in combination with analysis of the organisation's resource base, key information for strategic choice in the Decision Stage.

 

Tue 21/02/06

Fri 21/04/06

66%

 3.2

Resource & Capability Analysis

  1. To understand the organisation's strategic capability through analysis of resources.
  2. To ensure that strategic options can later be evaluated against realistic and feasible capabilities.

 

Tue 21/02/06

Wed 17/05/06

47%

 3.3

Stakeholder & Cultural Analysis

  1. To understand how the organisational culture will influence strategic choice
  2. To understand the expectations and conflicting interests of key stakeholders
  3. To assess the bases and configurations of power impacting the organisation
  4. To enable barriers and opponents of changes to be identified as a guide to evaluating strategic options.

 

Tue 21/02/06

Mon 24/04/06

64%

 

 

 

 

 

 

 

 

Products Completed.

ID

Name

Purpose

Start Date

End Date

 None

 

 

 

 

 

 

 

 

 

 

 Delivery Plans Next Period

Products Planned to start.

ID

Name

Purpose

Start Date

End Date

 None

 

 

 

 

 

 

 

 

 

 

Products Planned to continue work on.

ID

Name

Purpose

Start Date

End Date

 3.2

Resource & Capability Analysis

  1. To understand the organisation's strategic capability through analysis of resources.
  2. To ensure that strategic options can later be evaluated against realistic and feasible capabilities.

 

Tue 21/02/06

Wed 17/05/06

 

 

 

 

 

 

Products Planned to Complete.

ID

Name

Purpose

Start Date

End Date

 3.1

Environment Analysis

  1. To establish a view of the important external (and possibly internal) developments taking place around the organisation, including an understanding of why these are strategically significant.
  2. To develop an understanding of market opportunities which can be built on and threats which must be overcome or circumvented.
  3. To provide, in combination with analysis of the organisation's resource base, key information for strategic choice in the Decision Stage.

 

Tue 21/02/06

Fri 21/04/06

 3.3

Stakeholder & Cultural Analysis

  1. To understand how the organisational culture will influence strategic choice
  2. To understand the expectations and conflicting interests of key stakeholders
  3. To assess the bases and configurations of power impacting the organisation
  4. To enable barriers and opponents of changes to be identified as a guide to evaluating strategic options.

 

Tue 21/02/06

Mon 24/04/06

 

 

 

 

 

 

 


 

Project Risks.

Risk Movements Summary.

Risks

Open

Closed

Total

Brought Forward

15

0

15

New Risks Raised This Period

1

 

1

New Risks Closed This Period

(0)

0

 

Existing Risks Closed This Period

(1)

1

 

Carried Forward

15

1

16

 

New Risks raised in this period.

Id

Name

Expected Loss

Raised By

Date Raised

 Category

Event %

Impact %

Status

 16

Project Team personnel

 

Susan Smith - Marketing Director

20/03/2006

Organisational Management/Human Factors

50%

100%

Active

 

 

 

 

 

 

 

 

 

 

Risks Closed in this period.

Id

Name

Expected Loss

Raised By

Date Raised

 Category

Event %

Impact %

Status

Closed

 1

Project Management processes are not established and familiar

 

Susan Smith - Marketing Director

06/02/2006

Project Team Capability

70%

100%

Closed (Disappeared)

20/03/2006

 

 

 

 

 

 

 

 

 

 

 


 

Project Issues.

 

Issue Movements Summary.

Issues

Open

Closed

Total

Brought Forward

1

3

4

New Issues Raised This Period

8

 

8

New Issues Closed This Period

(3)

3

 

Existing Issues Closed This Period

(1)

1

 

Carried Forward

5

7

12

 

New Issues raised in this period.

The following new issues were raised and remained open at the end of this period.

Id

Name

Priority

Raised By

Date Raised

 Type

Impact

Status

 6

Problems in South American SBUs

3 - Nice not Vital

Andy Allen - Team Leader

13/03/2006

Issue

Medium

Inactive

 8

Delays in supply of external marketing info.

3 - Nice not Vital

Andy Allen - Team Leader

14/03/2006

Issue

Medium

Inactive

 10

Ellen Eastman sick leave

3 - Nice not Vital

Andy Allen - Team Leader

18/03/2006

Issue

Medium

Inactive

 11

Finance data incorrect

3 - Nice not Vital

Andy Allen - Team Leader

22/03/2006

Issue

Medium

Inactive

 12

Project X

1 - Must Have

Susan Smith - Marketing Director

27/03/2006

Request for Change

Medium

Inactive

 

 

 

 

 

 

 

 

 

The following new issues were raised and closed in this period.

Id

Name

Priority

Raised By

Date Raised

 Type

Impact

Status

Closed

 5

Business Continuity programme

3 - Nice not Vital

Andy Allen - Team Leader

06/03/2006

Issue

Medium

Closed (Answered)

17/03/2006

 7

Rework from revised outlooks

3 - Nice not Vital

Andy Allen - Team Leader

14/03/2006

Off-Specification

Medium

Closed (Implemented)

17/03/2006

 9

Need to be added to pressbox clippings updates

3 - Nice not Vital

Andy Allen - Team Leader

17/03/2006

Issue

Medium

Closed (Answered)

24/03/2006

 

 

 

 

 

 

 

 

 

 

 

Outstanding Issues closed in this period.

The following issues from prior periods were closed in this period;

Id

Name

Priority

Raised By

Date Raised

 Type

Impact

Status

Closed

 4

Change of ownership in Marine SBU

2 - Important

Andy Allen - Team Leader

27/02/2006

Issue

Low

Closed (Implemented)

10/03/2006

 

 

 

 

 

 

 

 

 

 

                               

 

End of Document

 








Home | Overview | Details | Downloads | Videos | Support | Training & Events | Purchase | Contact | Privacy Policy
Copyright © 2003-2009 Structured Project Management Solutions Ltd. All rights reserved.
PRINCE2™ is a Trade Mark of the Office of Government Commerce
All other product names, trademarks, or service names are registered by their respective manufacturers.