|
Back to Sample Outputs
Monthly Highlight Report
Below is an example of a more complex monthly highlight report produced by p2msp, showing the data automatically populated by p2msp.
HIGHLIGHT REPORT
|
Project Name |
p2msp Sample Project.mpp |
|
Release: |
Final |
Date: |
4th April 2006 |
|
|
|
|
Author: |
Susan Smith |
Company: |
XYZ Corporation |
|
|
|
|
Period From: |
01/03/2006 |
|
|
Period To: |
31/03/2006 |
|
|
|
|
|
|
Project Subject: |
Revised Corporate Strategy |
|
|
|
|
Project Category: |
|
|
|
|
|
Project Comments: |
Project Actuals updated to 31/03/2006 |
|
|
|
|
Document History |
|
Document: |
This document is only valid on the day it was printed.
|
Location: |
|
|
Revision History |
|
|
|
|
Revision Date |
Previous Revision Date |
Summary of Changes |
Changes Marked |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Distribution |
This document has been distributed to: |
|
|
|
|
Name |
Title |
Date of Issue |
Version |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Highlight Report
Purpose of Document
To provide the Project Board with a summary of the stage status at intervals defined by them.
Project status summary
Dates.
Start: |
Mon 16/01/06 |
Finish: |
Tue 08/08/06 |
Baseline Start: |
Mon 16/01/06 |
Baseline Finish: |
Thu 06/07/06 |
Actual Start: |
Mon 16/01/06 |
Actual Finish: |
NA |
Start Variance: |
0 days |
Finish Variance: |
23 days |
Duration.
Scheduled: |
147 days? |
Remaining: |
94.83 days? |
Baseline: |
124 days? |
Actual: |
52.17 days |
Variance: |
23 days? |
Percent Complete: |
35% |
Work.
Scheduled: |
4,048 hrs |
Remaining: |
2,520 hrs |
Baseline: |
3,664 hrs |
Actual: |
1,528 hrs |
Variance: |
384 hrs |
Percent Complete: |
35% |
Costs.
Scheduled: |
242,950.00 |
Remaining: |
141,270.00 |
Baseline: |
242,700.00 |
Actual: |
101,680.00 |
Variance: |
250.00 |
|
|
Earned Value.
Planned Value: |
104,458.06 |
Schedule Variance: |
-16,798.36 |
Earned Value: |
87,659.71 |
Schedule Variance %: |
-16% |
Actual Cost: |
101,026.27 |
Schedule Performance Index |
0.84 |
Budget at Completion: |
242,700.00 |
Cost Variance: |
-13,366.56 |
Estimate at Completion: |
279,707.48 |
Cost Variance %: |
-15% |
Variance at Completion: |
-37,007.48 |
Cost Performance Index: |
0.87 |
To Complete Performance Index: |
1.09 |
Delivery Progress This Period.
Products Started.
ID |
Name |
Purpose |
Start Date |
End Date |
% Complete |
None |
|
|
|
|
|
|
|
|
|
|
|
Products In-Progress.
ID |
Name |
Purpose |
Start Date |
End Date |
% Complete |
3.1 |
Environment Analysis |
- To establish a view of the important external (and possibly internal) developments taking place around the organisation, including an understanding of why these are strategically significant.
- To develop an understanding of market opportunities which can be built on and threats which must be overcome or circumvented.
- To provide, in combination with analysis of the organisation's resource base, key information for strategic choice in the Decision Stage.
|
Tue 21/02/06 |
Fri 21/04/06 |
66% |
3.2 |
Resource & Capability Analysis |
- To understand the organisation's strategic capability through analysis of resources.
- To ensure that strategic options can later be evaluated against realistic and feasible capabilities.
|
Tue 21/02/06 |
Wed 17/05/06 |
47% |
3.3 |
Stakeholder & Cultural Analysis |
- To understand how the organisational culture will influence strategic choice
- To understand the expectations and conflicting interests of key stakeholders
- To assess the bases and configurations of power impacting the organisation
- To enable barriers and opponents of changes to be identified as a guide to evaluating strategic options.
|
Tue 21/02/06 |
Mon 24/04/06 |
64% |
|
|
|
|
|
|
Products Completed.
ID |
Name |
Purpose |
Start Date |
End Date |
None |
|
|
|
|
|
|
|
|
|
Delivery Plans Next Period
Products Planned to start.
ID |
Name |
Purpose |
Start Date |
End Date |
None |
|
|
|
|
|
|
|
|
|
Products Planned to continue work on.
ID |
Name |
Purpose |
Start Date |
End Date |
3.2 |
Resource & Capability Analysis |
- To understand the organisation's strategic capability through analysis of resources.
- To ensure that strategic options can later be evaluated against realistic and feasible capabilities.
|
Tue 21/02/06 |
Wed 17/05/06 |
|
|
|
|
|
Products Planned to Complete.
ID |
Name |
Purpose |
Start Date |
End Date |
3.1 |
Environment Analysis |
- To establish a view of the important external (and possibly internal) developments taking place around the organisation, including an understanding of why these are strategically significant.
- To develop an understanding of market opportunities which can be built on and threats which must be overcome or circumvented.
- To provide, in combination with analysis of the organisation's resource base, key information for strategic choice in the Decision Stage.
|
Tue 21/02/06 |
Fri 21/04/06 |
3.3 |
Stakeholder & Cultural Analysis |
- To understand how the organisational culture will influence strategic choice
- To understand the expectations and conflicting interests of key stakeholders
- To assess the bases and configurations of power impacting the organisation
- To enable barriers and opponents of changes to be identified as a guide to evaluating strategic options.
|
Tue 21/02/06 |
Mon 24/04/06 |
|
|
|
|
|
Project Risks.
Risk Movements Summary.
Risks |
Open |
Closed |
Total |
Brought Forward |
15 |
0 |
15 |
New Risks Raised This Period |
1 |
|
1 |
New Risks Closed This Period |
(0) |
0 |
|
Existing Risks Closed This Period |
(1) |
1 |
|
Carried Forward |
15 |
1 |
16 |
New Risks raised in this period.
| Id |
Name |
Expected Loss |
Raised By |
Date Raised |
Category |
Event % |
Impact % |
Status |
16 |
Project Team personnel |
|
Susan Smith - Marketing Director |
20/03/2006 |
Organisational Management/Human Factors |
50% |
100% |
Active |
|
|
|
|
|
|
|
|
|
Risks Closed in this period.
| Id |
Name |
Expected Loss |
Raised By |
Date Raised |
Category |
Event % |
Impact % |
Status |
Closed |
1 |
Project Management processes are not established and familiar |
|
Susan Smith - Marketing Director |
06/02/2006 |
Project Team Capability |
70% |
100% |
Closed (Disappeared) |
20/03/2006 |
|
|
|
|
|
|
|
|
|
|
Project Issues.
Issue Movements Summary.
Issues |
Open |
Closed |
Total |
Brought Forward |
1 |
3 |
4 |
New Issues Raised This Period |
8 |
|
8 |
New Issues Closed This Period |
(3) |
3 |
|
Existing Issues Closed This Period |
(1) |
1 |
|
Carried Forward |
5 |
7 |
12 |
New Issues raised in this period.
The following new issues were raised and remained open at the end of this period.
| Id |
Name |
Priority |
Raised By |
Date Raised |
Type |
Impact |
Status |
6 |
Problems in South American SBUs |
3 - Nice not Vital |
Andy Allen - Team Leader |
13/03/2006 |
Issue |
Medium |
Inactive |
8 |
Delays in supply of external marketing info. |
3 - Nice not Vital |
Andy Allen - Team Leader |
14/03/2006 |
Issue |
Medium |
Inactive |
10 |
Ellen Eastman sick leave |
3 - Nice not Vital |
Andy Allen - Team Leader |
18/03/2006 |
Issue |
Medium |
Inactive |
11 |
Finance data incorrect |
3 - Nice not Vital |
Andy Allen - Team Leader |
22/03/2006 |
Issue |
Medium |
Inactive |
12 |
Project X |
1 - Must Have |
Susan Smith - Marketing Director |
27/03/2006 |
Request for Change |
Medium |
Inactive |
|
|
|
|
|
|
|
|
The following new issues were raised and closed in this period.
| Id |
Name |
Priority |
Raised By |
Date Raised |
Type |
Impact |
Status |
Closed |
5 |
Business Continuity programme |
3 - Nice not Vital |
Andy Allen - Team Leader |
06/03/2006 |
Issue |
Medium |
Closed (Answered) |
17/03/2006 |
7 |
Rework from revised outlooks |
3 - Nice not Vital |
Andy Allen - Team Leader |
14/03/2006 |
Off-Specification |
Medium |
Closed (Implemented) |
17/03/2006 |
9 |
Need to be added to pressbox clippings updates |
3 - Nice not Vital |
Andy Allen - Team Leader |
17/03/2006 |
Issue |
Medium |
Closed (Answered) |
24/03/2006 |
|
|
|
|
|
|
|
|
|
Outstanding Issues closed in this period.
The following issues from prior periods were closed in this period;
| Id |
Name |
Priority |
Raised By |
Date Raised |
Type |
Impact |
Status |
Closed |
4 |
Change of ownership in Marine SBU |
2 - Important |
Andy Allen - Team Leader |
27/02/2006 |
Issue |
Low |
Closed (Implemented) |
10/03/2006 |
|
|
|
|
|
|
|
|
|
End of Document
|