| |
|
|
|

p2msp Background
p2msp is the brainchild of Laurence Kelly,
founder and CEO of Structured Project Management Solutions, interviewed
here by Joe Pemberton about the origins of p2msp.
| JP: |
So when did
the idea for p2msp first come about? |
| LK: |
I first
started using the original Prince methodology on my projects and
programmes back in the early 1990s, using Ken Bradley's excellent book as a
reference, however it was the advent of Prince2 in 1996 that saw
things really start to take off. Even in those early days it was clear
that you needed to be both dedicated and well-organised to make Prince
work for you, and I was constantly looking for better ways to use the
method. |
| JP: |
Why
dedicated? |
| LK: |
As a working
Project Manager, one of the things I found most compelling about
Prince was the product based planning technique, because it addressed
the single most common problem I had seen on projects beforehand - the
problem of different people having different expectations and
assumptions about the project's deliverables. Often those
differences only came to light after a deliverable was
completed, which was generally disastrous for the project - lots of
rework required, maybe changes to earlier or later products, or
compromises on requirements, not to mention rounds of recriminations
and finger-pointing. All very costly and time-consuming, and
incredibly unproductive. This
common problem occurred not just with the end deliverables that the
project's customer receives, but even more so with the interim
deliverables that the project had to produce along the way - these
were often quite difficult, challenging & stretching products that
were not clearly defined and understood by all in the same way.
Product based planning struck a real chord with me from day one because it
recognises this key issue and sets out to resolve it, by establishing
a common understanding of the important aspects of deliverables
before the project starts work on producing them. The drawback of
course, is the additional time required up-front in planning the
project, compared to the quick alternative of producing a schedule
based on 'the information available at the time'. Most project
Sponsors want the work on their project to start ASAP after gaining
approval, and work in their eyes means producing the end deliverables, not
planning!
So you needed to be dedicated, because you often found you had to
fight for that additional time. |
| JP: |
Surely there
are other ways used to define deliverables, such as specifications? |
| LK: |
Well I
absolutely agree, but that's not how I see product based planning - if
you try to write a fully detailed specification for every product at
the planning stage, you'll never get started!
The way I see it is this: many projects,
especially large ones, start out as a vision of the future. That
vision is the endpoint of the project, and is usually articulated in
terms of how the endpoint looks and what benefits can be expected from
it once we have got there.
The aim of product based planning is to
transform that vision into describing a bridge built across a number
of stepping stones (the
Product Flow Diagram) that adds up to a coherent path showing how we
can get everyone and everything from today to the future without getting wet
- because every project execution has to cross the "river of risk" in
order to reach the endpoint vision. Each
stepping stone is important - you only need to fall in once for the
project to falter - so we
need to demonstrate that each stepping stone is credible enough for us to
commit to it : that's the purpose of the Product Description Forms.
They aren't detailed specifications of the product, just answers to
some basic & fundamental questions;
- What is its purpose?
- What does it consist of and look
like?
- How will we know it's completed OK?
- And most importantly, can we really
reach that distance from the previous product or stepping stone?
(You don't want to find out you can't halfway across)
|
| JP: |
I like your
'stepping stone' analogy - can you expand on it further? |
| LK: |
OK, well if I
was giving this as a high-tech presentation it would go something like
this; Slide Group 1 - The
Endpoint Vision
these slides show the endpoint vision that the project
sponsor is enthusiastically describing to his or her peers and
superiors in the boardroom, in order to sell the idea of the project.
I like to imagine this endpoint as a
glittering and futuristic building complete with full-motion 3D
fly-bys and walk-throughs that communicate the concept and its
benefits in an enthralling and convincing way. The building represents
the new company environment, whether it be a systems upgrade, new
product launch, M&A - or even a relocation project to a futuristic new
building!
The 3D vision of the future will be
presented to be as graphically realistic as an "artist's vision" can
possibly be - this helps not only to clarify some of the details but
also adds a feeling of realism - which subconsciously implies
achievability, because if we can see it and almost touch it, then
surely we can do it!
This first slide group ends with a
summary of the high-level estimated costs and timescales of the
project, followed by a usually more powerful summary of the projected
benefits (which will far outweigh the costs over time), and a quick
return to the glorious 3D endpoint. |
| JP: |
So the
concept is accepted & agreed and project approval is given, and now
you have a live project- -what happens next in terms of project
management and your 'stepping stone' analogy? |
| LK: |
Well, the
next step is to ensure we have analysed and and have a good
understanding of the journey that our project requires, so step 2 of
my presentation is; Slide
Group 2 - Analysing the Journey
these slides show the reality of the journey that needs to be
undertaken in order to achieve the project - this is what faces the
Project Manager at the start of a project.
I like to imagine these slides as first
showing a somewhat grim and depressing picture of the reality that is
today's pre-project environment - imagine a black & white portrayal of
a set of decrepit old factory sheds and prefab office buildings that
are loosely connected as a site, and just about manage to function as
a whole in order to do business.
We travel these decaying halls and
corridors of failing processes with our cerebral camera (still in
B&W), now & again focusing on the mundane & repetitive production line
tasks and archaic hand tools, and the struggling but still-smiling
faces of the unsung everyday heroes who keep this business running. At
this point our glittering colourful 3D endpoint seems to be a long,
long way away.
Now we move outside and scan the
horizon searching for the glittering future presented in Slide Group 1
- but there is no sign of it from this level. Pan left 360 degrees,
still no sign.
Luckily our cerebral camera allows us
to take to the air and zoom up and out from our surroundings (think
Google Earth), until we reach such an altitude that we can
finally see both our start and endpoint in the same frame. Depending
on the scope and scale of our project, we may have had to pass a
couple of satellites or even planets to achieve this, but whatever the
distance we can finally see it (if not then "Houston, we have a
problem ...")
Now that we can see both our start and
end points in view, we can mentally draw a line between them. That
line represents our project path and the distance & terrain that it
crosses represents our "landscape of risk".
Let's end this slide group with a more
zoomed-in detail view of the terrain of our project path - depending
on the size and scale it may be just a few miles with one 'river
of risk' to cross or it may be a few thousand miles with deserts,
mountains, canyons and seas in between.
It's important to get a good
understanding of what the distance and terrain of a project is before
even starting the project planning - this understanding may require
some up-front research and analysis for which you can find some
helpful suggestions in the analysis stage of our p2msp example project
which is part of the p2msp trial download.
How do you build such analysis and
planning of your project's journey into your overall plan? You need to
map out a 'Plan-the-Planning' stage whereby you allocate time &
resources to producing the elements of a product-based plan i.e. PBS /
PFD / PDs. You may also need to include a
'Plan-the-Plan-the-Planning'' stage - confusing but I'll come back to
this in more detail a bit later on. |
| JP: |
OK, that was
a bit long-winded. So now we have a birds-eye view of the journey
required for our project, what comes next? |
| LK: |
Apologies for
that, however I think it's all important stuff. What comes next is;
Slide Group 3 - Mapping the Journey.
These slides how what is involved in producing a product-based plan (PBS),
and how this planning approach starts to differ from producing a
work-based planning structure (or WBS).
This is where it gets difficult - this
is where we have to map out exactly how we get from A to B or from
start-point to endpoint. This is where Product Based Planning (PBP)
really shows its strength. There
are 3 logical steps to this PBP process, however in practice it is
fair to say that these three steps are normally an iterative process
which require a number of repetitions to get to a finished Product
Based Plan - and even then it is not a finished plan!
The three steps are;
1. Identify the products required (the
Product Breakdown Structure or PBS)
2. Specify the logical sequence of
production of the Products (the Product Flow Diagram or PFD)
3. Define what the products are by
producing a Product Description (or PD) for each product, which
provides enough detail to enable the author/producer to know exactly
what is required, and also how the quality of the finished product
will be measured (and accepted or rejected accordingly).
I cannot emphasise enough how important
it is to undertake each of these steps to the utmost, because the
outputs from this work will define the entire plan for the project -
if you get it wrong at this stage you will really suffer when it comes
to executing the plan. So,
returning to our slideshow analogy of 'Mapping the Journey' this is
where we plan out our series of 'base camps' on the way to achieving
our objective. Each of our 'Products' represents a 'base camp' for
that particular area of the project - a definable objective that can
be produced, reviewed and signed-off before we move on to the next
one. It's worth noting that there
is not just one single route on our project path - we need a separate
route for each area of the business which leads them to the end goal.
For example, if our project is a major
software upgrade which introduces new levels of integration and
functionality we might need a number of paths;
- a path for the software development
of the project, starting with an agreed requirements document and
culminating in a fully tested and working software product - there may
also be separate paths for the interim development and testing
deliverables - a path for the
end-user training requirements of the project, starting with a
Training Strategy document and culminating in fully trained set of
users able to operate the new application(s) - this may well include
a TNA (Training Needs Analysis) and a schedule of training courses
and attendees, as well as training course materials and examinations
and results etc. - a path for
the new hardware and infrastructure required for our project - again
this might start with a hardware/infrastructure strategy document
and culminate with the successful installation, testing and sign-off
of the required new hardware/infrastructure.
So Slide Group 3 in our multimedia
journey actually consists of four logically separate slides as
follows; |
| JP: |
Sorry to
interrupt, but when I said the last answer was a bit long-winded, that
was a lot shorter than this one! You said we were mapping the
journey, so far I don't see how we have done that... |
| LK: |
You are
absolutely right, I do get a bit carried away in the details... Ok to
put it simply
- The Products we define in the PBS
are our mapped-out nominated 'base camps' in our journey - they
describe where we will 'pitch our tents' before moving on to the
next goal. The PBS is normally drawn as hierarchical diagram where
each leg represents a particular area of the project - this enables
one to easily assimilate the scope and completeness of the project
plan.
- The PFD shows how we progress in
succession from one base camp to the next on towards the endpoint
goal - NB there will not be one single route but rather there will
be a separate route for each area of the business/project - however
all the routes will meet up at various points throughout and at the
end of the project. The PFD is often a cause of debate, normally
based around what degree of completeness is required in product A
before work can start on the subsequent product B. In reality
such decisions are expressions of risk-appetite - and starting work
on Product B before Product A is completed is always a degree of
risk - this should be noted in the Risk Log.
- The PDs describe what we expect each
base camp to consist of in detail - we need to be sure that it will
have not only all of the necessary sustainables, but also the
necessary building materials required to reach the next base camp...
And we need to get all of this
understood and signed off by all the key stakeholders before we even
start work on producing the Products! Now you can maybe see why
Product Based Planning requires more time up-front than the
traditional approach of 'just getting on with it'. |
| JP: |
Yes thank
you, I can see that!! So
tell me why would I as a project sponsor agree to all this additional
time and cost - let's face it, as far as I can see you don't yet even
have a Gantt Chart or resource plan yet!!!
I'm really losing patience now, I
want you to start work on delivering my project, not all of this
endless and pointless planning rubbish!!!!! You know there are plenty
of other Project Managers available out there!!!!. |
| LK: |
Wow - that is
familiar stuff - well done, you really got into the role of a
frustrated project sponsor there! |
| JP: |
Actually it
wasn't difficult - as far as I can see you have waffled on about the
need for endless planning, but so far nothing concrete has been
achieved at all. If I was a project sponsor holding the budget for
this, I would seriously be recruiting your replacement right now! |
| LK: |
And you would
be right to do so. Because I have
omitted the very first step I should have undertaken, which is to
explain to and agree with you - the Project Sponsor - exactly how and
why I want to approach the planning of this project, and to agree a
plan for the work involved in producing the plan.
In fact, I should probably have taken
one even earlier step in order to plan out how I was going approach
the planning activity and still ensure I kept all of the key
stakeholders and sponsors engaged and committed throughout the
planning process - this is known as the plan the planning of the
plan step which I mentioned much earlier. If you fail to do
this or otherwise get it wrong, you are likely to find yourself with
disgruntled and unhappy sponsors and stakeholders before you have even
started your project! |
| JP: |
OK so maybe I
should calm down and assume that you have explained all of this to me
already, so that I am happy with the overall process and where we
currently are. |
| LK: |
Exactly so -
there is a famous quote by Albert Einstein along the lines of "If I
had 1 hour to save the world, I would happily spend 55 minutes
thinking and 5 minutes in action", so he was definitely a believer in
good planning before execution!
So now we have completed Slide Group 3 - Mapping the Journey. We know
exactly what products are required from our project in order to reach
the end goal, and in what sequence. |
| JP: |
So what's the
next step? |
| LK: |
The next step
is; Slide Group 4 - Planning the
Journey |
|
|
|
New to Prince2?
Click here for more information about this hugely popular PM
Methodology
_______
New to MS-Project?
Click here for more information about the #1 project scheduling software
package
________

Prince2 Distance Learning
Practitioner - Accredited Training from just £299+VAT |
|