13th November 2008
Version 2008.1.8
- Fixed a problem that could cause an abend when
processing timesheet updates in Project Server
- Fixed a problem in the Product Description Form - if
the Task Generation option to assign resource & duration to the Product Task
was selected, the resource assignment was recreated each time you clicked
'OK' on the Product Description Form regardless of whether the data had
changed. If you use integration with MS-Outlook in MS-Project, this would
cause unnecessary update emails to be sent to the assigned resource.
- Fixed a bug in the PBS window where entering product
names on the PBS allowed you to enter a Line Feed character (via Ctrl+Enter)
which then caused an unexpected error.
- Fixed a bug in the process to export Issue Log to
Excel, where the field showing 'Other Projects Impacted' was instead
exporting the data for 'Other Products Impacted'.
- Fixed a problem that could cause an abend when saving
a project.
- Changed where some application & temporary files are
stored to aid with Windows Vista compatibility
- Added a new message and progress bar when producing
custom reports.
17th March 2008
Version 2008.1.7
- Fixed a problem that caused a crash when running
custom reports under MS-Project 2007 - this version of p2msp is the first
version that officially supports MS-Project 2007
- Changed the custom reports processing so that any
formatting on rich text fields in any p2msp forms is now also shown on
custom reports (for example the Purpose or Composition fields on the Product
Description Form) - prior to this release any rich text fields were only
shown as plain text on custom reports with no formatting.
- Change to store the Logo File pathname uniquely in
each project file - this means you can easily specify different logos for
different projects, and p2msp will display the appropriate logo whenever you
open that project file
- Added two new keywords for custom reports (<Logo> and
<LogoFullsize>) which enable you to automatically include the project logo
on your custom reports
- Fixed a problem that could occur when copying a
Product or a group of Products in the PBS screen - if any of the copied
products had sub-tasks with dependency links, additional dependency links
were erroneously created between the sub-tasks of the copied Product and the
new Product (thanks to Henk-Jan Molenkamp for finding this problem).
3rd February 2008
Version 2008.1.6
- Changed the Risk Impact Quantification
settings in the p2msp Options screen, so that these are now saved with your
individual project file - this means that you can easily specify different
settings for each project so that you can analyse your risks appropriately
according to the size & scale of your project, and your settings will be
remembered when you open your project file
- Fixed a problem where the default settings for
Library file pathnames could be incorrect - this would only occur if you
installed p2msp using a different user name than your own user name (e.g. by
using the Administrator account to install p2msp). We recommend that you
install p2msp by granting administrator privileges to your own account if
required.
- Fixed a problem where an unexpected error
might occur in unusual circumstances related to MS-Project Application
DisplayAlerts settings
- Fixed a problem which might occur whereby a
new issue or risk might erroneously inherit the same hyperlink for a related
document as a previously viewed issue or Risk
- Fixed a problem where the text displayed on an
optional message (i.e. one with a "Do not display this message again"
checkbox) might be truncated under unusual circumstances
- Fixed a problem where an unexpected error
might occur on a Risk Form when clicking "OK", if the Risk Short Name was >10
characters in length
17th July 2006
Version 2006.1.4
- added new options when
displaying PFD for current PBS view, to include connection points external to
the current view
- changed PBS views dropdown
in PBS toolbar to be a toolbar button
- Added 'Do not generate
sub-tasks' to Risk Form actions tab
- Improved context-sensitive
help via F1 key on any p2msp screen
13th July 2006
Version 2006.1.3
- added new options when
exporting a PBS diagram, to remove the on-screen colours and formatting from
the generated document
- fixed a minor problem
whereby Report Library reports could be run against an empty Issue or Risk
Log, causing an error - reports are now disabled if the log is empty
5th July 2006
Version 2006.1.2
- fixed a problem which
could occur when saving a project which contained no p2msp data
26th June 2006
Version 2006.1.1
-
new customisable Periodic
Reports can save you time by automating your regular project reporting such as
monthly Highlight reports
-
You can now arrange the
Product Breakdown Structure to get exactly the display you want via our new
PBS columns feature
-
Saving your own named views
of the PBS now includes all aspects of the view - zoom level, drawing style,
box shapes etc.
-
Data Storage methods are
improved, speeding up your file saves and offering easier options for Project
Server users
-
PFD views are improved so
that you can customise multiple views of the PFD to display exactly as you
want
- New Risk Map option to
plot Risks by a short name
- New option to Hide Issues
and Risks on the Gantt Chart when producing MS-Project reports
- New "Help" messages, which
can be switched off when no longer required
- In the PBS window, if you hover the cursor
over the PBS Views dropdown on the toolbar, it will display the name of the
currently select view as a tooltip.
- The Tasks Tab on the Product Description, Risk
& Issue Forms is always enabled, even if there are no tasks. This means you
can manually enter the initial tasks for a Product (or Issue or Risk) without
having to exit to MS-Project.
- A new Date Closed field has been added to Risk
and Issue Forms, which can be entered when closing an item - this new field is
used to drive the new periodic reporting for Risks and Issues. There is an
automatic conversion process for users upgrading from previous versions, which
will populate this field on existing closed Issues and Risks.
- Prior to this version, sub-tasks could only be
manually added to an active Issue or Risk. Now you can manually add sub-tasks
to an Issue or Risk regardless of its status.
- You can now right-click in an empty area of
the PBS window, this will open a popup menu which enables you to adjust
spacing between boxes in the PBS diagram.
- When you click on the main p2msp toolbar to
open any p2msp screen, the current MS-Project View, Filter and any Grouping
will be saved and later restored when you exit the p2msp screen.
- The range of custom report keywords for
standard and custom MS-Project fields has been extended to include all of the
new fields in Project 2003, including all Enterprise fields.
|
|
|
New to Prince2?
Click here for more information about this hugely popular PM
Methodology
_______
New to MS-Project?
Click here for more information about the #1 project scheduling software
package
________

Prince2 Distance Learning
Practitioner - Accredited Training from just £299+VAT |
|